South Osprey Avenue Force Main Replacement (4 months duration)

Project Details

Work Type: Sanitary Sewer Force Main Installation

Phase: Construction

Limits:

  • Along Bay View Drive from Pleasant Place to S. Osprey Avenue intersection to the intersection of S. Osprey Avenue and Alta Vista Street
  • Along S. Osprey Avenue from Old Oak Drive intersection to Alta Vista Street.
    intersection.
  • Along Old Oak Drive and Spring Creek Drive from Siesta Drive to S. Osprey
    Avenue.

City: Sarasota

County: Sarasota

Construction Cost: $___________

Construction Start: Summer 2025

Est. Completion: Fall 2025

About

The City of Sarasota Utilities Department is replacing the force main along South Osprey Avenue to improve the collection system capacity, resilience, and sustainability.

The project includes:

  • Extending an existing 8-inch PVC force main from Lift Station 2 with approximately 960 linear feet of 10-inch HDPE force main along Bay View Drive from Pleasant Place to S. Osprey Avenue intersection to the intersection of S. Osprey Avenue and Alta Vista Street.
  • Installing new 6,200 linear feet of 14-inch HDPE force main from S. Osprey Avenue and Webber Street intersection to Alta Vista Street intersection (via Horizontal Directional Drilling- HDD.)
  • Replacing approximately 2,700 LF of 8-inch PVC force main with 10-inch PVC force main (via open cut) from Siesta Drive and Old Oak Drive intersection along Spring Creek Drive to the S. Osprey Avenue intersection.

 

Contact

Communications Team
Devyn M. Brown, PE

Construction Project Manager
Georges Nicolas, PE

For Media Inquiries Only
Jan Thornburg

Share This