South Osprey Avenue Force Main Replacement (4 months duration)
Project Details
Work Type: Sanitary Sewer Force Main Installation
Phase: Construction
Limits:
- Along Bay View Dr from Pleasant Pl. to S. Osprey Ave. intersection to the intersection of S. Osprey Ave. and Alta Vista.
- Along S. Osprey Ave. from Old Oak Dr. intersection to Alta Vista
intersection - Along Old Oak Dr. and Spring Creek Drive from Siesta Dr to S. Osprey
Ave.
City: Sarasota
County: Sarasota
Construction Cost: $___________
Construction Start: Summer 2025
Est. Completion: Fall 2025
About
The City of Sarasota Utilities Department is replacing the force main along South Osprey to improve the collection system capacity, resilience, and sustainability.
The project includes:
- Extending an existing 8-inch PVC force main from Lift Station 2 with approximately 960 linear feet of 10-inch HDPE force main along Bay View Dr from Pleasant Pl. to S. Osprey Ave intersection to the intersection of S. Osprey Ave. and Alta Vista.
- Installing new 6,200 linear feet of 14-inch HDPE force main from S. Osprey & Webber St intersection to Alta Vista intersection (via Horizontal Directional Drilling- HDD.)
- Replacing approximately 2,700 LF of 8-inch PVC force main with 10-inch PVC force main (via open cut) from Siesta Dr & Old Oak intersection along Spring Creek Drive to South Dr & S. Osprey Ave intersection.