South Osprey Avenue Force Main Replacement (4 months duration)

Project Details

Work Type: Sanitary Sewer Force Main Installation

Phase: Construction

Limits:

  • Along Bay View Dr from Pleasant Pl. to S. Osprey Ave. intersection to the intersection of S. Osprey Ave. and Alta Vista.
  • Along S. Osprey Ave. from Old Oak Dr. intersection to Alta Vista
    intersection
  • Along Old Oak Dr. and Spring Creek Drive from Siesta Dr to S. Osprey
    Ave.

City: Sarasota

County: Sarasota

Construction Cost: $___________

Construction Start: Summer 2025

Est. Completion: Fall 2025

About

The City of Sarasota Utilities Department is replacing the force main along South Osprey to improve the collection system capacity, resilience, and sustainability.

The project includes:

  • Extending an existing 8-inch PVC force main from Lift Station 2 with approximately 960 linear feet of 10-inch HDPE force main along Bay View Dr from Pleasant Pl. to S. Osprey Ave intersection to the intersection of S. Osprey Ave. and Alta Vista.
  • Installing new 6,200 linear feet of 14-inch HDPE force main from S. Osprey & Webber St intersection to Alta Vista intersection (via Horizontal Directional Drilling- HDD.)
  • Replacing approximately 2,700 LF of 8-inch PVC force main with 10-inch PVC force main (via open cut) from Siesta Dr & Old Oak intersection along Spring Creek Drive to South Dr & S. Osprey Ave intersection.

 